Williams Trace Reconstruction Phase I

Update: March 21, 2017

Sugar Mill Drive - Traffic Detour
Sugar Mill Drive will close at the intersection of Williams Trace from March 29 until April 13 to allow for storm sewer installation and paving of the intersection. Traffic will be detoured to Planters Street.

Residents are asked to be mindful of work crews, expect traffic delays, and when possible, avoid the area to prevent traffic congestion. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.


----------------------------------------------
Update: March 8, 2017
Stephens Grant Dr. - Traffic Detour - This detour has been cancelled.
Stephens Grant Dr. will be closed at the intersection of Sweetwater Blvd. on March 9. Starting at 8 a.m. traffic will detour to Austin Parkway until 5 p.m. Storm sewer installation work across the intersection will take place.

----------------------------------------------

Update: January 30, 2017
Williams Trace Blvd. - Traffic Switch
A traffic switch will be implemented on Williams Trace Blvd. from State Highway 6 through the intersection of Austin Parkway on February 8. This traffic change is expected to last approximately six months. Vehicular traffic on the northbound half of the boulevard will be switched to two way traffic to allow for the reconstruction of utilities, drainage, and paving in the southbound lanes.

----------------------------------------------
Initial Communication
Phase I of the Williams Trace Reconstruction project is scheduled to begin on January 2017. The overall scope of the project is as follows:
  • Full replacement of the roadway, from SH 6 through Austin Parkway
  • Full replacement of the existing water main (due to age and material type)
  • Upgrade of the existing traffic signals at Austin Parkway
  • Construction of an additional parallel storm sewer along the project corridor to correct drainage deficiencies
  • Construction of a 10-ft sidepath along Williams Trace from Austin Parkway to SH6
Updates will be posted on this website in addition to advance notices given for temporary water service outages and road closures.

Project documentation is available below:
Project: Williams Trace Reconstruction Phase I, CIP # ST1408
Project Manager: Ross Woodfin
Engineering Department: (281) 275-2780