Construction/Maintenance Updates

Posted on: October 19, 2022

Street Rehabilitation – W. Airport Blvd.

Street rehabilitation work will be taking place on W. Airport Blvd. starting October 24 and is expected to last through February 2023. Traffic lane closures can be expected through the duration of the project. The project will have three phases, each approximately lasting 1 – 2 months:

  1. Burney Rd. to Eldridge
  2. Eldridge to Gillingham
  3. Gillingham to Dairy Ashford

Residents are asked to be mindful of work crews, expect traffic delays, and when possible, avoid the area to prevent traffic congestion. Visit its.sugarlandtx.gov for more information on Sugar Land travel time data.

Operations Manager: Matthew Douglas, 281-275-2577
Project Manager: Daniel Benson, 281-275-2845
Public Works: 281-275-2469
311 Contact Center: 311 or 281-275-2900