Sugar Land, TX – Sugar Land has made significant progress on $46 million in drainage projects approved by voters in 2019.
Construction of several projects is complete, including the first phase of Sugar Creek drainage improvements, Greatwood Village drainage improvements and flood control improvements at Dam III. Drainage improvements for New Territory and Chatham Avenue are nearing completion.
All other projects authorized by voters have been designed and will soon be scheduled for construction.
The projects included in the propositions were selected based on extensive planning through various master plans, City Council input and the results of citizen satisfaction surveys that indicated drainage was among the top priorities for residents.
Project Name | Design Status | Construction Status | Completion Date |
---|
Sugar Creek Drainage Improvements at Montclair Drive - Phase I
| 100% | 100% | October 2022 |
Sugar Creek Drainage Improvements at Montclair Drive - Phase II
| 100%
| 0% | Fall 2023 |
Greatwood Village Drainage Improvements
| 100%
| 100% | October 2022 |
Riverbend Stormwater Inlets and Pipe Replacement -Phase I
| 100%
| 40% | Spring 2023 |
Flood control Improvements at Dam III
| 100%
| 100% | Fall 2019 |
Austin Park/Chimneystone Drainage Improvements
| 90% | 0% | Spring 2024 |
Avalon Brazos Landing/Commonwealth Drainage Improvements - Phase I
| 80% | 0% | Spring 2024 |
Avalon Brazos Landing/Commonwealth Drainage Improvements - Phase II
| 80% | 0% | Spring 2024 |
Covington West and Imperial Woods Drainage Improvements
| 70% | 0% | Fall 2023 |
Citywide Flood Prevention and Drainage Studies
| 50% | N/A | N/A |
Drainage Improvements for New Territory & Chatham Avenue
| 100% | 95% | November 2022 |
Learn more details about each project.