2019 Bond Projects

Project Statuses

Completed

14

In Design

4

Under Construction

2

Last Update: February 24, 2026

Proposition A – Drainage Projects

10 Projects | 47.6 Million

Project Name
Phase / Completion Date
Cost ($)
Sugar Creek Drainage Improvements - Montclair Dr. 
Project Summary 
Completed
8.8M
Riverbend Stormwater Inlets and Pipe Replacement
Project Summary
Completed
3.5M
Flood Control Improvements - Dam III Oyster Creek @ Lexington
Project Summary
Completed
0.8M
Austin Park/Chimneystone Drainage Improvements
Project Summary
Completed
16.5M
Greatwood Village Drainage Improvements 
Project Summary 
Completed
3M
Avalon/Brazos Landing/Commonwealth Drainage Improvements
Phase I - Lake Control Structure Modification
Project Summary
Design / Winter 2027
1.1M
Avalon/Brazos Landing/Commonwealth Drainage Improvements
Phase II - Elkins Road
Project Summary
Design / Winter 2027
7.3M
Telfair Drainage Improvements - New Territory Blvd & Chatham
Project Summary
Completed
3M
Covington Drainage Improvements – Covington West & Imperial Woods
Project Summary
Completed
3M
Citywide Flood Prevention & Drainage Studies
Project Summary
Completed
0.6M
Total Drainage Projects
 
47.6M
(S) Study  (D) Design  (C) Construction    

Proposition B - Public Safety/Public Facility Projects

4 projects | 26.3 Million

Project Name
Phase / Completion Date
Cost ($)
Emergency Operations Center/Public Safety Dispatch Building
Project Summary
Design / TBD
11.5M
Public Safety Training Facility – Phase II
Project Summary
Completed
10M
Public Safety & Public Services Building Rehabilitation
Project Summary
Completed
3M
Fire/EMS Apparatus Replacement
Project Summary
Completed
1.8M
Total Facilities Projects
 
26.3M
(S) Study (D) Design (C) Construction  (E) Equipment Purchase    

Proposition C - Streets Projects

5 Projects | 10.26 Million

Project Name
Phase / Completion Date
Cost ($)
Country Club Blvd Improvements - Sugar Creek to Chesterfield
Project Summary
Completed
1.7M
University Blvd Widening – FBC Mobility Bond Project
Construction / Summer 2026
1.7M
Soldiers Field Extension to SH 6 / Roundabout at First Colony Blvd
and Soldiers Field
Construction / Fall 2027
2.46M
Major Streets Rehabilitation
Project Summary
Complete
4M
Citywide Transportation & Mobility Studies
Project Summary
Complete
0.4M
Total Streets Projects
 
10.26M
(S) Study (D) Design (C) Construction    

Proposition D - Animal Shelter

1 Project | 6.6 Million

Project Name
Phase / Completion Date
Cost ($)
Animal Shelter
Project Summary
Design / Fall 2027
6.6M
Total Animal Shelter Project
 
6.6M
(S) Study (D) Design (C) Construction