PROJECT: Lexington Roundabout Project – C.I.P. No ST0701
CONTRACTOR: Jerdon Construction Co
NOTIFICATION:
Lexington Boulevard at Oxbow Drive
Construction continues strong as weather permits. The completion date was moved from December to February due to in large part an intentional delayed start to assist and allow the bridge construction crew access across the intersection to take delivery of a long lead item fabricated off site which after meeting with the bridge crew was determined that it could not be delivered from University due to the size and complexity of how it was to be off loaded, as well as allow for the concrete trucks to continue with their final deliveries, and some constructability issues which you normally have on all projects.
Crews will finish up installing sidewalks and retaining walls soon , weather permitting, before pavers and landscaping are installed.