PROPOSITION B PROJECT
Sweetwater Blvd Phase I (Austin Pkwy to Palm Royale)
$5.475M

The Pavement Management and Maintenance Program (PMMP) was developed to assist in extending the usable life of pavement infrastructure through strategic maintenance practices including pavement replacement.

Sweetwater Blvd

2024 Bond Project

Based on guidance from the PMMP, this project involves street reconstruction and installation of a 10-foot side path on one side extending from Austin Parkway to Palm Royale including a connection to the First Colony Trail project.

Funding: 2023 FBC Mobility Bond - $4,500,000; 2024 GO Bond - $5,475,000
Project Manager: Sagnik Raha
CIP #: CST2801

ESTIMATED CONSTRUCTION START
OCT 2028

CURRENT PROJECT PHASE
PER/STUDY

Learn more about project phases

ESTIMATED COMPLETION
APR 2030